Released 25 October 2022
Request:
Could you please provide an update on the New Hospital Programme at your relevant hospital?
- When was the original target set for this to be finished?
- When was the planning permission applicant submitted?
- If planning permission has been granted, what date was that received?
- Is the project forecast to be completed by the original target date?
- Has a location been identified for the new hospital?
- Please provide information on whether a planning application has been a) submitted b) accepted or rejected.
Information disclosed:
Please note the following information relates to the 3Ts redevelopment at the Royal Sussex County Hospital site, Brighton:
- Summer 2020 for Stage 1 of a 3 Stage programme.
- December 2011
- March 2012
- No, Stage 1 if the programme is due to open Spring 2023. Stages 2 and 3 are under development with the Completion date to be agreed.
- Yes, the location was identified prior to applying for planning permission.
- Answered under question 3 above.